February start for two projects in Papanui
7 February 2025

Work is set to continue on the railway level crossing upgrades along the Northern Line cycleway route. Sawyers Arms Road is the last of the three upgrades, which also included the crossings on Harewood and Langdons roads last year. Read below about the Sawyers Arms Road level crossing upgrade, including traffic impacts, as well as details on minor watermain pipe relocation works happening on Langdons Road (night works). |
Sawyers Arms Road level crossing upgrade Traffic impactsWork hours will generally be between the hours of 7am and 7pm. For Stages 1 and 3, the traffic impacts are the same, and the road will be reinstated back to two-way outside of work hours. A 30km/h speed limit will be in place to keep workers and everyone safe. Please be on the lookout for changes in traffic management and follow the signs. Stage 1: Monday 10 February until Friday 28 February
Stage 2: Saturday 1 March until Sunday 16 March
Stage 3: Monday 17 March until Friday 11 April (Same impacts as Stage 1) |
What's happeningThe Sawyers Arms Road railway level crossing is being upgraded to improve safety and access for pedestrians and cyclists using the Northern Line cycleway, which runs along the railway corridor. What's being installing: | |
|
Other improvements: Widening the shared path areas, putting in new ducting and drainage, renewing kerb and channel; making landscaping enhancements and completing a range of engineering improvements to the railway crossing. Cycle connections: Where there is a painted cycle lane connecting the Northern Line cycleway with the Papanui Parallel cycleway, a separate cycle lane will be constructed to upgrade this important link in the cycleway network. These upgrades will help to ensure everyone can get to where they need to go, safely and easily. We expect the new traffic lights will be operational in mid-2025. |
Watermain pipe relocation works on Langdons Road What's happeningIn mid-February, there will be work on the westbound lane of Langdons Road to relocate an underground watermain pipe. The watermain pipe is currently running through the inside of the stormwater pipe, which is a high risk to the water network in the case of an extreme weather event. It needs to be removed from the stormwater pipe and reinstalled underneath the stormwater pipe. The work will involve excavation, pipe removal, pipe laying, backfilling, and restoration works. This will be completed across three (to five) nights, from 16 February (7pm) to—at the latest— the morning of 21 February (6am). Completing the work at night helps to minimise the disruption to road users and makes it safer for the contractors carrying out the work as there is less traffic at night. Traffic impactsNight (7pm to 6am):
Please allow more travel time if you are travelling on Langdons Road between 7pm and 6am or take a different route if you are able to. Day (6am to 7pm): No impact during the day.
|
Stay in the loop You can stay up-to-date by visiting the Council website project webpage, which has more information. Thanks for your patience while this work is completed. |