Thanks to everyone who submitted feedback on this project

We received a total of 37 submissions about Bromley street upgrades (Bromley Road and Keighleys Road), from 35 individuals and the following organisations:

  • Canterbury Memorial Gardens and Crematorium
  • Spokes

What you told us

65% of submitters said they supported or somewhat supported the plan for Keighleys Road and Bromley Road. 30% said that they did not support the plan.

Common topics raised during consultation were:

  • That the plan will result in slower/safer speeds in the area (14)
  • Support for upgrades around Bromley School (8)
  • That the plan will make the area feel and/or be safer for locals (7)
  • Support for speed humps specifically (5)
  • The upgrades are unneeded (5)
  • It is a waste of money (5)

You can read more about what we heard in the meeting agenda below, which includes the staff report. To read all the feedback we received, download the submission table below.

Decision made

Waitai Coastal-Burwood-Linwood Community Board approved this project, on 9 December 2024.

The Community Board also made the following resolutions:

  • Request that staff investigate options for improving the berm on Keighleys Road on the side where it boarders the cemetery.
  • Requests that staff investigate options for plantings to improve the amenity of the road improvements.
  • Note: Council is working on a Bromley Traffic Plan and currently has Ruru and Maces Roads on the renewal schedule.

You can read the meeting minutes which include the formal resolutions councillive.ccc.govt.nz

You can also watch the decision being made. Waitai Coastal-Burwood-Linwood Community Board decision meeting - 9 December (from 2hr, 2m).

What happens next?

We expect construction of these improvements to begin in early 2025.